Garden Archives—Click
here to see archived garden pages |
Current—Click
Current to see current progress |
Sources—Click
Sources for links to the houseplans and elevations |
|
|
Archives—click on a date to see that day’s progress |
December 2007 |
|
December
30 & 31,
2007—We play house at the cottage |
|
December
28, 2007—I
bring beds to the cottage |
|
December
26, 2007—Boxing
Day at the site |
|
December
21, 2007—Solstice
at the site |
|
December
19, 2007—Gloom & cold
don’t stop the progress |
|
December
14, 2007—I
view things from a higher plane |
|
December
12, 2007—Our
ceiling beams are hung (for better or for worse) |
|
December
7, 2007—We
get our shower floor |
|
December
5, 2007—The carport goes up |
|
November 2007 |
|
November
30, 2007—Finally,
we have running water! |
|
November
28, 2007—The
sheathing continues |
|
November
23, 2007—We
have walls! |
|
November
16, 2007—Exterior
framing is almost complete |
|
November
14, 2007—The
great
“ear” debate begins |
|
November
9, 2007—The
utility wing gets its ears! |
|
November
7, 2007—We
are above it all . . . |
|
November
2, 2007—More sheer and some plumbing |
|
October 2007 |
|
October 31,
2007—Halloween
at the site |
|
October 26,
2007—Framing
the living room—and more |
|
October 24,
2007—Framing
resumes |
|
October 19,
2007—Rained
out! |
|
October 17,
2007—The
house is suddenly very tall . . . |
|
October 12,
2007—When
it rains, it pours! |
|
October
10, 2007—Framing
begins, despite a little rain |
|
October 5,
2007—The
slab dries in the sun . . . |
|
October
2 & 3,
2007—The floor is poured! |
|
September 2007 |
|
September
28, 2007—Ready
for the pour |
|
September
26, 2007—Tubing
for radiant heating is laid |
|
September
21—The
crew begins to install void-form and slab insulation |
|
September
18 & 19,
2007—Grade-beams, cottage plaster finished and more . . . |
|
September
7, 2007—Work
on the grade-beam cages almost complete |
|
September
5, 2007—More
progress on grade-beam cages |
|
August 2007 |
|
August
29, 2007—Plumbing
disaster averted |
|
August
24, 2007 —Trenching
for the main house grade-beams begins |
|
August
22, 2007 —The
main house piers are bored |
|
August
17, 2007 —The
main house is positioned |
|
August 15,
2007—Kai
starts installing trim |
|
August
10,
2007—Preparations for the giant fête |
|
August
3 , 2007—Paint
preparation picks up |
|
August
1 , 2007—The
propane tank arrives |
|
July 2007 |
|
July 27,
2007—Drywall
in the cottage too |
|
July 25,
2007—Drywall
and soy-based polyurethane! |
|
July 20,
2007—The
barn gets puffy |
|
July 18,
2007—Rain
in July! |
|
July 13,
2007—Terra-forming
and drainage |
|
July 11,
2007—Sprinklers
and stairs and more . . . |
|
July 6, 2007 —Ducting
installed |
|
June 2007 |
|
June 27,
2007—Much activity at the site |
|
June 22,
2007—Appliances
arrive (and an emergency) |
|
June 20,
2007—The
barn gets stripes |
|
June 15,
2007—We
start to get wired |
|
June 13,
2007—The
barn turns brown |
|
June 8, 2007—The
wood is put up on the cottage bay window |
|
June 6, 2007—Getting
ready for the Tyvek inspection |
|
June
1, 2007—We get County approval for our exterior color |
|
May 2007 |
|
May 30, 2007—The
roofers came, they saw and they roofed |
|
May 25, 2007—Siding
is complete on the 1st floor of the barn |
|
May 23, 2007—The
barn gets windows |
|
May 16, 2007—Starting
up again |
|
May 9, 2007—Still on stand-by |
|
May 4, 2007—All
quiet on the western front . . . |
|
May 2, 2007—The roof sheathing goes on |
|
April 2007 |
|
April 27,
2007 —The
Guest Cottage Roof Trusses Arrive |
|
April 25, 2007—Big events at the site! |
|
April
20, 2007—The barn roof goes up |
|
April 18,
2007 —Now we have a ceiling, too |
|
April 13,
2007—We have walls! |
|
April 9 2007 —Forming
up the barn and guest cottage slabs |
|
March 2007 |
|
March 28—Things
get started . . . |
|